The Town of Hinton is thrilled to share that the log-awaited library installation is just around the corner! The handcrafted log structures, built with care offsite, are now ready to be installed at the forever home. Here’s what to expect in the coming days:  

  • Sunday, December 14
    • Crews and equipment arrive on site
  • Monday, December 15
    • 8 a.m.
      • On-site work begins
    • 3 p.m.
      • Welder, crane and loaded trailer arrive on site. The truck will be parked in front of the library parking lot until installation begins.
  • Tuesday, December 16 to Thursday, December 18
    • Construction continues, please watch for equipment and workers at work

Library Access During Construction  

The Library will remain open and accessible throughout the installation process. To ensure a smooth visit, use an alternative route: 

  • Enter through the main entrance of Dr.Duncan Murray Recreation Centre and walk down the SHA hallway towards the library. The doors that are usually closed will be open during this construction period.
  • The east-side entryway near Gordon Moore Park will also be accessible to the Library during this time.

Please plan ahead and allow extra time to navigate these routes. We appreciate your patience and cooperation as we log in to this construction work.  