Trans Mountain Construction in Hinton

Pipeline map - Transmountain

From Trans Mountain. Last updated: June 30, 2022.

West of Obed to West of Hinton Pipeline Construction

Work at this site is currently underway. Work is taking place in a series of phased activities along the pipeline right-of-way west of Obed to west of Hinton. This could include surveying, flagging and staking the right-of-way, mobilization of crews and equipment, preparing the right-of-way, clearing and grading, delivery and staging of pipe, trenching, welding, lowering of pipe, backfilling and restoration of the right-of-way.

For more information on pipeline construction and its various stages, click here.

Hinton Pump Station

Work at this site is currently underway. Work is taking place within the existing footprint of our pump station and includes clearing, installing fencing, installing piles and pouring concrete, installing mechanical equipment, piping and welding, construction of structural steel and buildings, electrical installation and instrumentation, and restoration of the site.

View Trans Mountain's interactive map and a full list of construction updates in the community at www.transmountain.com/yellowhead-county.